Using the PERT method review the following data for a project that should be scheduled using CPM:
b. What is the critical pat
Using the PERT method review the following data for a project that should be scheduled using CPM: b. What is the critical path? c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 16 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.) Probability


We have an Answer from Expert

View Expert Answer

Expert Answer


a. The PERT method is a project scheduling technique that uses th