(Solved): Table 1. A U.S. manufacturing company operating a subsidiary in an LDC (less-developed country) sho ...
Table 1. A U.S. manufacturing company operating a subsidiary in an LDC (less-developed country) shows the following results: Sales (units) Labor (hours) Raw materials (currency) Capital equipment (hours) Question 1, 2 use Table 1 1. Calculate partial labor and capital productivity figures for the parent and subsidiary. (Round your answers to 2 decimal places.) C D 3. The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A B E F 2. Compute the multifactor productivity figures for labor and capital together. (Round your answers to 2 decimal places.) G A A C B. D D E.F 5 0062320 U.S. 8 105,000 19,750 $21,100 59,250 4 a. What is the critical path? A+B+E+G=22 b. How many weeks will it take to complete the project? FC LDC 19,900 14,750 19,750 4,750
3. The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 5 8 4 6 ABCO esc ? ? ? D E F G A+C+D+F+G=24 A A a. What is the critical path? A+B+E+G=22 b. How many weeks will it take to complete the project? C B.D D E.F *E c. How much slack does activity B have? 11 2 3 6 900 F2 ?? # 80 F3 di $ 4 % 5 a FS ^ FA
Solution (1) : Let Calculate the partial labor and capital productivity for parent and subsidiary : • Labor productivity for parent = Sales/Labor hours = 105,000/19,750 = 5.32 units/hr • Labor p