Home / Expert Answers / Operations Management / suppose-that-rafay-is-only-given-5-weeks-nbsp-instead-of-7-to-complete-the-project-by-how-pa882

(Solved): Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how ...



Suppose that Rafay is only given

5 weeks? (instead of 7?) to complete the project. By how many weeks should each activity be crashed in order to meet the? deadline? Assume that you can crash an activity down to 0 weeks duration.

Activity : A,B,C,D,E,F

Each Activity should be reduced by ___ weeks

What is the total crashing cost? $_____

 

The following is a table of activities associated with a project at Rafay Ishfaqs software firm in Chicago, their durations,

The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: \begin{tabular}{cccc} \hline Activity & Duration (weeks) & Precedes & Crash Cost/Week \\ \hline A (start) & 1 & B, C & \( \$ 400 \) \\ B & 1 & E & \( \$ 100 \) \\ C & 4 & F & \( \$ 200 \) \\ E & 2 & F & \( \$ 300 \) \\ F (end) & 2 & \( - \) & \( \$ 400 \) \\ \hline \end{tabular} Suppose that Rafay is only given 5 weeks (instead of 7 ) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. \begin{tabular}{cc} \hline Activity & Each Activity Should be Reduced BY (days) \\ \hline A & \( \square \) week(s) \end{tabular}


We have an Answer from Expert

View Expert Answer

Expert Answer


Accord
We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe