Question (4): Draw a sketch to show the characteristic of the following target cost contract, in addition draw the expected final price curve according to the following: cost increase share =75% by owner, share saving =15% by contractor, GMC =290,000SR, GMP =300,000SR, minimum fee =10,000SR, target cost =200,000SR, and maximum fee =35,000SR Analysis the following situations: a) If cost =295,000SR, find the project profit and price b) If profit =25,000SR, find the project cost and price c) If price =200,000SR, find the project cost and profit