(Solved): Perform earned value analysis using the details presented below and calculate BCWS, BCWP, ACWP, Sche ...



Perform earned value analysis using the details presented below and calculate BCWS, BCWP, ACWP, Schedule Performance Index and Cost Performance Index

.student submitted image, transcription available below

The project status at the end of 5 working days is presented below:

i) Activity A : 100% done, used 3 workers/day at the cost of Rs. 650 / day
ii) Activity B: 30% done, used 7 workers/day at the cost of Rs. 650 / day
iii) Activity C : 80% done, used 6 workers /day at the cost of Rs. 650 per day
iv) Activity D: not yet started;
1.BCWS at the project level as on status date:

A.18200

B.18400

C.18600

D18800

2.ACWP at the project level as of status date:

A.29000

B.29250

C.29500

D.29750

SPI and CPI values are

A.SPI is 0.7 and CPI is 0.4

B.SPI is 0.9 and CPI is 0.6

C.SPI is 1.1 and CPI is 0.8

D.SPI is 1.3 and CPI is 1.0

BCWP at the project level as on status date:

A12640

B.12660

C.12680

D12700

CHOOSE THE RIGHT OPTIONS IN EACH ONE QUESTION RELATED TO PROJECT MANAGENT

\begin{tabular}{|c|c|c|c|c|c|} \hline \begin{tabular}{c} Activity \\ ID \end{tabular} & Name & Duration & Predecessors & \begin{tabular}{c} No of workers \\ required per \\ day \end{tabular} & \begin{tabular}{c} Resource cost planned \\ INR/day \end{tabular} \\ \hline 1 & Start & 0 & - & - & 600 \\ \hline 2 & A & 2 & Start & 2 & 600 \\ \hline 3 & B & 5 & A & 5 & 600 \\ \hline 4 & C & 3 & A & 4 & 600 \\ \hline 5 & D & 2 & B,C & 2 & \\ \hline 6 & Finish & 0 & D & - & \\ \hline \end{tabular}