Home / Expert Answers / Economics / nbsp-question-5-the-cpi-and-spi-figures-for-random-projects-are-tabled-below-use-these-values-pa830

(Solved):   Question 5 The CPI and SPI figures for random projects are tabled below. Use these values ...



Question 5
The CPI and SPI figures for random projects are tabled below. Use these values to interpret the progress of these

 

Question 5 The CPI and SPI figures for random projects are tabled below. Use these values to interpret the progress of these projects (variance indices) by completing the blank spaces:


We have an Answer from Expert

View Expert Answer

Expert Answer


CPI = 0.53 SPI=1.256 The project is over budget by 47% and behind schedule by 24%. CPI=1 SPI=1.94 The project is on budget but behind schedule by 94%. CPI=1.36 SPI=0.823 The project is on budget but ahead of schedule by 17%.
We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe