(Solved): Management:Network diagram:For the given network / activity diagram:Calculate and show the early sta ...



Management:

Network diagram:

For the given network / activity diagram:

  1. Calculate and show the early start time for activity D
  2. Calculate and show the late start time for activity F
  3. Calculate and show the early finish time for activity G.
  4. Calculate and show the late finish time for activity C.
  5. Determine the slack time for activity D.


We have an Answer from Expert

View Expert Answer

Expert Answer



For the given data, the CPM (critical path method) analysis can be performed as follows,

Formulate th...