Kostelnik Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $237,000, variable manufacturing overhead of $3.90 per machine-hour, and 30,000 machine-hours. The company has provided the following data concerning Job A496 which was recently completed: Number of units in the job. 20 Total machine-hours 80 Direct materials $500 Direct labor cost $2,160 The unit product cost for Job A496 is closest to: (Round your intermediate calculations to 2 decimal places.) O $180.20 O $45.05 O $133.00 O $72.20