Given is a CPM project network diagram as shown below. Start A B Activity Start A day 10 C D a) The Project Completion time= b) The Earliest Start time, ES, of Activity G= d) The critical activities are c) The Latest Finish time, LF, of Acitivity C= LLE D G days H days. days. End (ex. Fill in answer as ABCD) End