(Solved): From the following information, develop an AON project network. Complete the forward and backward ...



From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slac

From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?


We have an Answer from Expert

View Expert Answer

Expert Answer


1. To develop an AON project network.From the following data, project network can be shown as follows:ABCDEComputing Forward pass and backward pass-In