Draw a CPM network for the project and indentify critical activities. \( \quad \) See below. Critical activity is ACDEGH What

Draw a CPM network for the project and indentify critical activities. \( \quad \) See below. Critical activity is ACDEGH What is the duration of the project under normal conditions? 77 days What is the total cost of the project under normal completion? 117 thousand If the project needs to be crashed for three days, which activities should be expedited? What would be the total cost of project after crashing for three days?


We have an Answer from Expert

View Expert Answer

Expert Answer


There are six critical activities as given