(Solved): Develop a resource schedule using as your template the loading chart below. Use the parallel method ...
Develop a resource schedule using as your template the loading chart below. Use the parallel method and heuristics given. Be sure t update each period as the computer would do. Note: activities use the resource skills as shown in the network diagram. Three of the resource skills are available.
Schedule resource load chart with ES and slack updates Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. A resource scheduled beyond the shaded area will delay the project. "TP" stands for time period.
List the order in which you scheduled the activities of the project
Which activities are now critical? ? 1 2 2 ? 3 2 4 ? 5 ? 6 Recompute your slack for each activity given your new schedule. What is the slack for: