Home /
Expert Answers /
Civil Engineering /
determine-the-amount-of-excavation-needed-for-the-spread-footing-presented-below-a-three-foot-work-pa675
(Solved): Determine the amount of excavation needed for the spread footing presented below. A three-foot work ...
Determine the amount of excavation needed for the spread footing presented below. A three-foot working distance is required, and the excavation will be sloped 1:1.75 (1.75 vertical foot for every horizontal foot).