Consider the Lab Experiment Project depicted in Figure 8-4. Based on the information provided, what is the expected duration

Consider the Lab Experiment Project depicted in Figure 8-4. Based on the information provided, what is the expected duration of this project? a. 24 days b. 26 days c. 28 days d. 22 days


We have an Answer from Expert

View Expert Answer

Expert Answer


The correct option is (a) 24 days Explanation: The paths and the path lengths of the project are