Consider a project Gantt chart with the following conditions (see Figure 1 below). Susan is your o ...
Consider a project Gantt chart with the following conditions (see Figure 1 below). Susan is your only programmer, and she is responsible for Activities 3 and 4 , which overlap. In resource-leveling the project so that Susan is only working a maximum of 8 hours each day, what would the new Gantt chart look like? What would be the new project completion date? Figure 1