Canine Kennels Company (CKC) manufactures two different types of dog chew toys ( and , sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, , and ) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid per hour. Total labor costs per week are fixed. Variable overhead costs are . The plant operates one 8 -hour shift per day, or 40 hours/week. rurchased part Which of the three workstations, W, , or has the highest aggregate workload, and thus serves as the bottleneck for CKC? with a total load time of minutes. (Enter your response as an integer.)


We have an Answer from Expert

View Expert Answer

Expert Answer



Based on the case provided, it can be determined that X is the workstation with the highest aggregate workload.

Each workstation can be computed based on its load e, and hence consideration of the time spent on processing for each product needs to be considered at the workstation and for each product's demand. Therefore ;
For workstation W,
The processing time for Product A is 2 minutes per unit.
The processing time for Product B is 1 minute per unit.
The total demand for the product per week for B is 1,500 units of A and 1,000 units of B.
Hence, the load time can be computed by: Load time = + (1 x 1,000) + (2 x 1,500) = 4,000 minutes.