\begin{tabular}{|c|c|c|c|} \hline Activity & Description & Immediate Predecessor & Time (weeks) \\ \hline A & Survey building site & & 7 \\ \hline B & Develop initial design & & 10 \\ \hline C & Obtain board approval & A, B & 13 \\ \hline D & Select architect & C & 4 \\ \hline E & Establish budget & C & 6 \\ \hline F & Finalize design & D, E & 13 \\ \hline G & Obtain financing & E & 11 \\ \hline H & Hire contractor & F, G & 7 \\ \hline \end{tabular}
(c) Develop the activity schedule for the project. The expected completion time is \( 55 \quad \vee \quad \) weeks, which is less \( \checkmark \checkmark \) than 1 year.