(Solved):
A three station work cell is illustrated in the image above. A unit needs to ...
???????
A three station work cell is illustrated in the image above. A unit needs to be processed at either Machine A or Machine B for Station 1 (parallel lines, both lines doing the exact same thing). The unit is then processed at Stations 2 and 3 before leaving the work cell. The process time of each machine/station is indicated in the flowchart. What is the process time of this system measured in minutes/unit? Note: 1- Do not include the unit of measure in the answer. For instance, if the answer is 4.6min/ unit only enter 4.6.