A project for improving a billing process has the following precedence relationships and activity times:
a. Choose the correc
a. Choose the correct network diagram below.
b. Calculate the slack for each activity. Which activities are on the critical path?
A project for improving a billing process has the following precedence relationships and activity times: a. Choose the correct network diagram below. a. Choose the correct network diagram below. b. Calculate the slack for each activity. Which activities are on the critical path?


We have an Answer from Expert

View Expert Answer

Expert Answer


Option (A) is incorrect because activity H has two immediate predecessors, while option (A) has only one immediate predecessor, activity G. Option (B)