3) A commercial vehicle body manufacturer has secured a project to produce the production schedule shown below. This is a new
3) A commercial vehicle body manufacturer has secured a project to produce the production schedule shown below. This is a new product and the first unit took \( 1,000 \mathrm{hrs} \) to produce but the company estimates that it can achieve a PR of \( 80 \% \) a) Estimate the number of hours required to complete the \( 38^{\mathrm{m}} \) unit b) Assuming an employee works on average \( 150 \mathrm{hrs} \) per month. The budget has allowed a maximum of 30 direct labour employees in a month and 15,000 direct labour hours for the project. Will the budget be adequate? 4) A maintenance manager has produced the following schedule for fitting inverters to a company's process pump drives. If the PR is estimated from similar projects at \( 90 \% \). The budget allows 40 employees to be employed on the project and a total of 8,000 hours. Assume an average of 40 hours working hours per week. If the first unit took 30 , hrs to convert is the schedule feasible, and if not, can it be altered? Are there any additional costs involved?


We have an Answer from Expert

View Expert Answer

Expert Answer


Production of first unit took 1000 hrs Production rate achievable 80% For the six months period Total Units Produce