13. In projects with adaptive life cycles, many of the project management processes are repeated in each iteration of the project except: A. Develop Project Charter B. Collect Requirements C. Define Scope D. Create WBS 14. Which of the following is not an input to the Develop Project Charter process A. Agreements B. Business Case C. Benefits D. Stakeholder register management plan 15. Which of the following is an enterprise environmental factor A. Configuration B. Change control C. Historical D. Commercial databases management knowledge procedures information base 16. The project management team has determined that there are some changes to the scope of the project. According to the PMBOK, who is responsible for reviewing, evaluating, and approving documented changes to the project? Change Control Board B. Change Configuration C. Scope Control D. Configuration Contr (CCB) Board (CCB) Board (SCB) Board (CCB)